Coastal Path Progress
Lydgate Park to Lihi boat ramp
www.kauaipath.org

December 2010
Happy Holidays!
New estimated completion near June 2011


An overlook view of the bridge construction from the south.



From the south shore of Wailua River you can see that the structural Acrow sections have been completed over the river to the north bank.



All of the exposed concrete surfaces will be covered with lava rock veneer enhancing the look of the bridge. (See two photos above.)



The road surface planks are being installed over the Acrow sections. At the time of these photos, approximately half of the bridge is covered.


October 2010

From the front page of the October 6 issue of The Garden Island newspaper.

The Acrow panels are being installed on the old bridge and to the new side braces.


August 2010


The most noticeable item completed is the crossing at the driveway entrance to the southern end of Wailua Beach. This is looking north with Kuhio Highway to the left and the ocean to the right.


Looking south toward the river and bridge construction.


Right now, it's hard to imagine what the path will look like leading up to the "train bridge."


Gecko images have been cast into the edges of the crossing.


Sub-surface drilling is still going on. There is no hard foundation or path surface here yet.


The view from the beach up the Wailua River under the bridge.


It appears concrete pouring forms are being built at the ends of the cantilever supports.


This photo was taken looking south between the two bridges. Off in the distance on the opposite bank you can see the remains of an old concrete footing from the first bridge that crossed Wailua River.


Spring 2010

Changes to the Wailua River "train" bridge were started last year by the State. This will not only provide a pedestrian connection across the river, but also add another vehicular traffic lane to Kuhio Highway so that there will be two lanes in each direction to ease congestion.


From the southern (Lihue) side of Wailua River, the concrete is being poured where the highway "bends" to line up with the bridge.


Braces have been added to each side of the narrow bridge so that wider, pre-stressed concrete planks will be supported. The original planks had to be changed to accommodate 2 vehicular lanes and the path.


Photos from the previous phase's construction (2009)